A scratch dig callout (often printed as scratch/dig) is a surface-acceptance requirement, not a complete polishing recipe. It tells the supplier how certain visible surface imperfections are to be limited and inspected under a specified rule. The familiar notation “60-40” or “20-10” is often used in optical procurement, but the numbers are meaningful only when the purchase order or drawing identifies the governing specification and inspection conditions.
This distinction prevents a common quoting mistake: treating a grade as a universal measure of optical performance. Surface imperfections are only one part of a finished optic. Figure, roughness, coating condition, aperture, material and function may have separate requirements. A part can meet a stated scratch dig grade and still fail its drawing for another reason. Read the scratch dig notation with the rest of the drawing. Record the scratch dig criterion before polishing begins.
What the two numbers describe
Under MIL-PRF-13830B, the first number is the scratch number and the second is the dig number. NASA-HDBK-6007B reproduces the specification’s table and explains the number grades as maximum scratch width and maximum dig diameter. In that table, 60 corresponds to a maximum scratch width of 6 µm and a maximum dig diameter of 600 µm; 40 corresponds to 4 µm and 400 µm. The same pattern gives 20-10 as 2 µm maximum scratch width and 100 µm maximum dig diameter when the pair is read under that specification.
Those dimensions help explain why “20-10” is generally a tighter imperfection limit than “60-40” in this convention. They are not a direct prediction of contrast, scatter, wavefront error or system performance. A scratch can be long and narrow; a dig is a localized defect whose diameter is assessed. Defect shape, position, orientation, illumination and the optical system’s sensitivity can affect functional impact even when two surfaces carry the same nominal grade. A scratch dig number is therefore an acceptance shorthand, not a complete optical performance specification.

The exact limits above apply to the cited MIL table. Do not copy them into a contract that cites another standard or an in-house rule without checking that document’s definitions. A “60-40” label without a reference can be ambiguous across suppliers, industries and legacy drawing practices. Ask for the document number, revision and any customer-specific inspection instructions before comparing quotations. When buyers request a scratch dig grade, attach the governing source to the purchase requirement.
How this relates to ISO 10110-7
ISO 10110-7:2017 addresses the indication of acceptable levels of surface imperfections within a test region on optical elements and assemblies. The standard defines drawing notation for this subject; it should not be casually treated as interchangeable with every MIL-PRF-13830B contract callout. If the drawing cites ISO 10110-7, interpret the notation using that edition and the drawing’s stated method. If it cites MIL-PRF-13830B or a customer specification, apply that contract document instead. Do not convert a scratch dig grade from a supplier’s catalog into an ISO callout without an approved cross-reference.
For procurement, record four items together: the grade or notation, the governing document and revision, the surface or test region to inspect, and the inspection conditions. If the drawing references a standard but omits a needed evaluation detail, raise the question before production. Replacing one notation with another based on a shorthand chart can silently change the acceptance basis.
If a drawing also includes dimensional, centering, wedge or thickness callouts, interpret each under its own referenced requirement. Scratch/dig notation does not replace those separate characteristics.
Why inspection conditions matter
Scratch dig inspection is a visual acceptance process performed under defined conditions. The applicable document or customer procedure may specify illumination, viewing geometry, magnification, comparison standards, test region and how borderline defects are judged. Inspectors should use the same controlled method across incoming checks, process checks and final acceptance. A bright phone light, a microscope image with unknown scale or a photograph compressed for messaging is not an equivalent acceptance test.
The inspector also needs to know which surface is being assessed and whether the optic is coated. Handling marks, residue, particles and reflections can be mistaken for defects or can hide them. Clean the part using the approved method, avoid touching the optical aperture, and inspect with the required setup. If a mark changes or disappears after cleaning, record that observation according to the procedure rather than relabeling it informally.
When comparing two suppliers, ask for the inspection method and record format, not just a statement that the part is “20-10.” Confirm who supplies the comparison standard, how the inspected region is defined, how reinspection is handled, and what happens when a defect lies near the acceptance boundary. These questions make the requirement reproducible and reduce disputes caused by different shop-floor interpretations.
What polishing can and cannot control
Polishing can remove or reduce some surface damage left by fine grinding, but the result depends on the starting surface, material, tool, abrasive process, part support and inspection method. A more aggressive process is not automatically safer: it may change figure, edge condition or dimensions. The incoming surface and the stock available for finishing therefore matter alongside the final defect limit.
Scratch dig performance is not controlled by the polishing machine alone. Abrasive contamination, worn or damaged tools, poor cleaning, handling, blocking residue and contact with fixtures can all introduce or reveal imperfections. Separate the source of a defect from the station where it was found. A final inspection may discover a mark created earlier; that does not prove the polishing step caused it.
If a batch fails, preserve representative parts and document the inspection setup before changing the process. Map each defect to its location and appearance, review cleaning and handling records, and compare the affected surface with parts that passed. Then test one controlled change at a time. This approach helps distinguish a tooling issue from contamination, incoming damage or a measurement disagreement.
Where the polishing machine fits
The optical lens polishing machine range covers different polishing geometries and part envelopes. For example, the FP-6U is an upper-swing machine for concave lenses, with six independently controlled axes; the FP-4U is a four-axis upper-swing machine with a documented spindle-speed range of 450–3,000 rpm. These are equipment configuration facts. They do not certify a scratch dig grade or prove that a finished part will pass inspection.
Use a representative sample to establish the process window for the material, geometry and incoming condition. Define the polishing tool and compound, verify cleaning between steps, and inspect parts using the same acceptance method named in the order. The machine supports the motion and contact needed for the process; the inspection rule determines how surface imperfections are accepted.
The FP-6U six-spindle optical polishing machine is one example in the range. It is relevant when the part geometry and batch justify parallel concave-lens processing. Machine selection should be based on radius, diameter, workholding, batch size and process evidence—not on a promise that a spindle count guarantees a surface grade.
Video — Concave Lens Polishing Machine FP-4U – Four-Spindle Polishing with Auto Loading
Before release, check the drawing and purchase order for the following:
- The exact grade or notation, including number order.
- The governing standard, revision and any customer-specific additions.
- The surface, aperture or test region covered by the requirement.
- The inspection conditions, comparison reference and reporting method.
- The process route and who owns cleaning, handling and final inspection.
If one item is missing, request clarification instead of assuming that a familiar label fills the gap. Keep the chosen notation and inspection method attached to the same drawing revision used by production and quality.
For process review, provide the material, part geometry, incoming surface condition, target drawing revision, required grade and inspection procedure. The team can review the polishing route and define a free sample cutting or finishing evaluation where appropriate; acceptance still follows the customer’s specified inspection method.
Frequently asked questions
What do 60-40 and 20-10 indicate?
They are scratch/dig surface-acceptance grades interpreted under the applicable inspection specification. The exact rule and conditions should be stated in the purchase requirement.
Does a scratch/dig grade specify a polishing recipe?
No. It defines an acceptance criterion, not the process settings needed to achieve it.
Can two inspections be compared without matching conditions?
Not reliably. Lighting, magnification, viewing method and governing specification affect evaluation; use the stated inspection conditions.
Sources checked
- ISO 10110-7:2017, Surface imperfections — scope and current-edition status.
- NASA-HDBK-6007B — reproduces the MIL-PRF-13830B scratch/dig grade table; the contract’s cited standard governs acceptance.
- Optical lens polishing machine range — public product range and machine-role evidence.
- FP-6U product page — public FP-6U configuration evidence.